File #: ID# 19-352    Version: 1 Name:
Type: Council Consent Calendar Status: Passed
File created: 10/1/2019 In control: City Council / Successor Agency
On agenda: 10/8/2019 Final action: 10/8/2019
Title: Authorize the City Manager to execute Change Order #1 in the amount of $70,248.19 for additional remodeling work to the Lake Elsinore Neighborhood Center (CIP Project #Z20015)
Attachments: 1. Change Order #1 - SR, 2. Change Order #1 - Exhibit A - Change Order Form

Title

Authorize the City Manager to execute Change Order #1 in the amount of $70,248.19 for additional remodeling work to the Lake Elsinore Neighborhood Center (CIP Project #Z20015)

 

Recommended Action

Authorize the City Manager to execute Change Order #1 in the amount of $70,248.19 with Corner Keystone Construction Corporation for additional remodeling work to the Lake Elsinore Neighborhood Center Project.