Title
SB 821 Mission Trail Signing & Striping Project CIP Project No. Z10051
Recommended Action
1. Award the Public Works Construction Agreement for the SB 821 Mission Trail Signing and Striping Project to J & S Company; and,
2. Authorize the City Manager to execute the Agreement in the amount of $16,392.00 to J & S Striping Company, in substantially the form attached and in such final form as approved by the City Attorney; and,
3. Authorize the City Manager to execute change orders not to exceed the 10 percent contingency amount of $1,640.00; and,
4. Authorize the City Engineer to record the Notice of Completion once it is determined the work is complete and the improvements are accepted in the City maintained roadway network.